NEW YORK, July 1 (Xinhua) -- The rebuilding of the World Trade Center site
in New York will run late, the New York Times reported Tuesday.
Quoting the Port Authority of New York and New Jersey, which owns the site,
the report said that the "schedule and cost for each of the public projects on
the site face significant delays and cost overruns."
The 2.5-billion-dollar PATH station and transit hub nearby are not only
behind schedule and over budget, but the final design is not even finished, said
the report.
Furthermore, on the south side of the site, the demolition of the Deutsche
Bank tower will not be completed until sometime next year, at least 14 months
behind schedule.
The report noted that the Port Authority adamantly refused to offer new
schedules or cost estimates, but some officials had said the delays could run up
to three years.
The cost overruns could extend into the billions for a project whose total
cost is now more than 15 billion dollars, it said.
The newspaper quoted a 34-page report issued by the Port Authority of New
York and New Jersey on Monday as saying that at the heart of the problems were
overly ambitious completion dates that were probably inaccurate from the day
they were announced.
Although Port Authority officials publicly acknowledged the daunting
problems on Monday, they were also eager to convey the sense that some progress
was being made on the centerpiece, the 1,776-foot-tall Freedom Tower, as well as
on three other office towers, the transit hub and the foundations for the
memorial.
"The World Trade Center site is being rebuilt, will continue to be rebuilt,
and it will be completed," Christopher O. Ward, executive director of the Port
Authority, was quoted as saying on Monday. "The question surrounding the World
Trade Center rebuilding is not if all of the projects will be built, rather when
and for how much."