BEIJING, Jan. 28 -- The blue-colored National
Aquatics Center (NAC), nicknamed the "Water Cube" and located by Beijing's North
Fourth Ring Road, was inaugurated and delivered for use on the morning of
January 28, 2008.
It took over four years to construct the Olympic
venue, which is a new landmark in Beijing.
 |
|
A worker takes photographs under the
Olympic diving platforms during the inauguration ceremony of the National
Aquatics Centre in Beijing Jan. 28, 2008. China officially unveiled
its bubble-wrapped National Aquatics Centre, nicknamed the "Water Cube,"
on Monday, one of the two iconic venues for this year's Beijing
Olympics. (Photo: chinadaily.com.cn/Agencies) Photo Gallery>>>
|
The project's ETFE air cushion structures are the
first of their kind to be used in China and the largest and most complicated
membrane system in any single project in the world.
With the efforts of various participants, many
scientific and technical difficulties were overcome. Among the achievements,
nine important self-dependent innovations resolved world-class difficult topics
related to the project's steel structures, membrane structures and inner layout,
formulated related work procedures and technical regulations, and filled in the
gap in China's field of architecture.
Also, the NAC is the only Olympic venue to be funded
by donations from compatriots. It reflects the great unity of the Chinese at
home and abroad to stage the Olympic Games through joint efforts.
Located on the southern part of the central area of
the Olympic Green in Beijing, the NAC has a planned construction area of 6.95
hectares. Being adjacent to the central axis of the city, the NAC is situated on
par with the National Stadium, at an equal distance to the axis.
 |
|
An overview of the Olympic swimming pool
and diving platforms during the inauguration ceremony of the National
Aquatics Centre in Beijing Jan. 28, 2008. (Photo:
chinadaily.com.cn/Agencies) Photo Gallery>>>
|
The NAC's Games-time construction area is close to
80,000 square meters, containing 17,000 standard seats, including 6,000
permanent seats and 11,000 temporary ones. During the 2008 Olympic Games, it
will produce 42 gold medals in swimming, diving and synchronized swimming.
After the Olympics, it will be converted into a
multi-functional facility for sports, culture and recreation, featuring a "water
setting" for members of society.
On January 31, the NAC will host its first Good Luck
Beijing sport event -- the 2008 Swimming China Open.
Timeline of events for the National Aquatics Center
(NAC):
-- In July 2003, the design project of the NAC is
officially settled.
-- On December 24, 2003, the NAC breaks ground and
begins earthworks.
-- In May 2005, the NAC's main concrete structure is
completed.
-- In June 2005, installation of the steel structure
begins in the NAC.
-- On April 10, 2006, the main structure of the NAC
is topped off, and its steel structure is installed.
-- On June 16, 2006, the supportive structures of the
NAC are removed.
-- On August 1, 2006, the first air cushion is
installed on the NAC.
-- On December 26, 2006, the membrane structures are
installed on the outside of the NAC.
-- In January 2007, the decoration and fit-up process
begins in the NAC.
-- In March 2007, the municipal engineering works
begin in the NAC.
-- In September 2007, the electro-mechanical
equipment is installed in the NAC.
-- On January 28, 2008, the NAC is inaugurated and
delivered for use.
(Source: BOCOG)