WASHINGTON, April 30 (Xinhua) -- The U.S. project to
rebuild Iraq remains far short of its targets, leaving the country plagued by
power outage, inadequate oil production, shortages of clean water and heath
care, the Washington Post quoted a report by a U.S. government oversight agency
as saying Monday.
The 232-page quarterly review by the Special
Inspector General for Iraq Reconstruction presents a sobering picture of the
challenges of reconstruction in a war zone.
The inspector general's report lays out how even
successful endeavors -- for example, the completion of more than 800 school
projects and training for thousands of teachers -- haven't realized their
potential because of security risks.
During four years of insurgency and sectarian
fighting, less than a third of Iraq's 3.5 million students attended class,
according to the report, which cited Iraqi Education Ministry statistics.
The report found that almost all of the nearly 20
billion U.S. dollars in reconstruction funds appropriated by Congress in 2003
has been allocated. More than half of the projects to be undertaken with that
money have been completed, while many more are underway.
In the medical field, only 15 of 141 primary
health-care centers have been completed -- and only eight of those are open to
the public -- while 126 projects are slated to be finished by the end of the
year.
As in past reports, the inspector general's office
found that some of the most significant reconstruction shortfalls were in
electricity production. "Electricity has the longest way to go," special
inspector general Stuart W. Bowen Jr. said in an interview Friday.
Before the U.S.-led invasion, Iraq's power system
produced 4,500 megawatts a day with an aging infrastructure in which 85 percent
of power plants were at least 20 years old, the report said.
Reconstruction officials initially hoped to increase
daily output to 6,750 megawatts by the summer of 2004, a target later lowered to
6,000 megawatts. But in the most recent quarter, Iraq generated only 3,823
megawatts per day.
The shortage was particularly acute in Baghdad.
Before the war, the city received an average of 16 to 24 hours of power a day.
Last spring, Baghdad averaged eight hours of electricity a day.
This year, during the last week of March, the city
received only 6.5 hours a day. The rest of the country, however, received an
average of 14 hours of power a day.
Security problems have affected many areas of
reconstruction, the report said, making construction difficult and hindering
projects slated for completion over the next year and a half.
The U.S. Defense Department reported an average of
1.4 attacks per week on critical infrastructure in the electricity, water, oil
and gas sectors.
Although the rate is lower than it was before
political authority was restored to Iraqi leadership in mid-2004, the attacks
are more severe and cause greater disruption, said the report.
Iraq also continues to miss goals set for producing
oil and gas, the report said. This past quarter, oil output averaged 2.6 million
barrels per day, compared with the U.S. target of three million. Oil exports
account for nearly all the Iraqi government's income.
The U.S. has spent almost two billion dollars to
provide drinkable water and improve sewer systems. The goal of reconstruction
was to bring clean water to 8.4 million Iraqis, but with 88 percent of potable
water projects complete. The current figure is 5.6 million, according to the
report.
In other areas, the report cites success. Bank
officials were trained in distributing small-business loans. Automated
tax-collection and accounting systems were installed. veterinary clinics were
renovated. And 114 border forts have been completed.